Front replacement of coal support plate(material 16mn,V-shaped groove,CO2 protection welding,correction,polishing and leveling)
5.5 meter coal loading truck
1、Maintenance content:
1.Front replacement of coal support plate(material 16mn,V-shaped groove,CO2 protection welding,correction,polishing and leveling)
2.Slide rail replacement under the coal board(material 16mn)
2、Personnel composition:
1.Welding,calibration,materials,and technical guidance are provided by____ Responsible.
2.1-2 cranes(25 tons)are employed by the factory.
3.The disassembly and assembly shall be coordinated by the coking section of the factory.
4.Commander in Chief___ However,the site and personnel are___ Responsible.
3、Precautions for 5.5-meter coal loading truck:
1.Personnel should be allocated according to the actual situation,not too many,but relatively fixed.
2.Irrelevant personnel are not allowed to enter the site.
3.Staff should wear hats and protective equipment.
4.Strictly prevent falling during lifting,and personnel are not allowed to be under the lifted object.
5.Welding and cutting shall follow the welding and cutting regulations.
6.Pay attention to electricity usage.
7.Strictly prevent scratches and tool falls.
Ordinary coking enterprises all have the problem of high energy consumption and heavy pollution.At th...
The cold coke discharge device is installed at the bottom of the dry quenching tank to discharge the ...
Half of the air pollution on the top of coking equipment accessories is caused by the escape of raw g...